2nd March 2011

Ground floor structure completed. This concists of pre cast concrete 'I' beams with polystyrene blocks laid between. The cavity in the external wall will be filled with mineral wool insulation.


This shows the shape of the polystyrene blocks. They are designed to wrap underneath the concrete beams thus providing continuity of insulation.

3rd February 2011

Foundations in and blockwork up to ground floor slab level